Date | Milestone |
June 13st, 2022 | MISO issues Dynamics Data Request |
June 27th, 2022 | Stakeholders complete Dynamics Data Request |
July 18th, 2022 | MISO posts draft PSSE and TSAT Dynamics cases for Stakeholder review |
July 25th, 2022 | Stakeholders comments due |
July 26th, 2022 | MISO incorporate changes |
July 29th, 2022 | MISO post final PSSE and TSAT Dynamics cases |
Date |
Milestone |
Responsible Party |
08/29/2022 |
LSE, TO, and GO data request sent |
MISO |
08/29/2022 |
Model On Demand reference models posted |
MISO |
09/09/2022 |
Generator data due to Model On Demand |
GO |
09/23/2022 |
Load profiles due to Model On Demand |
LSE |
09/23/2022 |
Transmission project, BLG profile, and device profile data due to Model On Demand |
TO |
10/14/2022 |
Topology and Load Pass model posted for review |
MISO |
10/14/2022 – 10/31/2022 |
Review Topology and Load Pass models/updates to MOD |
LSE, TO, and GO |
12/16/2022 |
Review Pass 3 models posted for review |
MISO |
12/16/2022 - 01/31/2023 |
Review of Review Pass models, respond to data checks/updates to MOD |
LSE, TO, and GO |
03/17/2023 |
Final MISO models completed/posted |
MISO |