In the March 12, 2024, meeting of the Interconnection Process Working Group (IPWG) stakeholders were invited to review and submit feedback on Recommended IBR Performance Requirements (PAC-2024-2).
Please provide feedback on the following:
Please provide feedback by March 29, 2024.
For the IPWG IBR performance requirements and the PMU data requirement:
DTE appreciates the opportunity to provide feedback on MISO’s proposed performance requirements for adoption covering voltage and frequency support, consecutive voltage deviation ride-through, and measurement. We have the following questions and concerns:
We would like for MISO to address the concerns that we have listed above and we look forward to further discussion on this very important topic.
Arevon appreciates the opportunity to provide feedback on MISO’s proposed IBR performance requirements.
Generally speaking, Arevon thinks that MISO has appropriately identified the performance requirements on which it should move forward (Slide 5 of MISO’s March 13, 2024 presentation at the IPWG – “Presentation”). There are a couple of specific points Arevon would like to make.
First, with respect to the maximum step response time within the suggested range of 1 – 30 seconds (Slide 8 of the Presentation), Arevon believes that MISO should start with 30 seconds. Since these will be new requirements, MISO should start conservatively and make future adjustments as necessary and feasible.
Second, with respect to the reaction time performance target of less than 200 ms, not all IBR resources can achieve this (DC coupled battery storage systems, for example). MISO should be careful not to establish across the board IBR requirements that can’t be met by all IBR resource types.
Savion, LLC (“Savion”), a Shell Group portfolio company, is an industry-leading utility-scale solar and energy storage project development company. Savion appreciates the opportunity to provide input on “Recommended IBR Performance Requirements (PAC-2024-2)”. Savion agrees and support the implementation of IEEE2800. However, Savion would like some clarification on this matter.
Transmission Owners Feedback on Inverter-Based Resource Performance Requirements
March 29, 2024
At the March 12, 2024 meeting of the Interconnection Process Working Group (IPWG), MISO requested the following feedback on proposed IBR Performance Requirements:
The MISO Transmission Owners (TOs or Owners) appreciates MISO’s efforts to establish footprint wide requirements for Inverter-Based Resource Performance, as many Owners already have established these requirements, and consistency in both the requirements and the execution of these requirements throughout the footprint would be a welcome improvement to both the Generator Interconnection Process and the accuracy of transmission planning models. In response to the questions posed by MISO in the IPWG Stakeholder Feedback Request, the Owners offer the following:
The Owners support MISO’s proposal to update its basic Inverter-Based Resource Performance Requirements to incorporate the IEEE P2800 Standard, the Owners agree with MISO’s overview of the issue and support MISO’s program. While many Transmission Owners’ Planning Criteria addresses these issues the Owners would prefer MISO-wide requirements and consistent execution.
When the Generating Facility is physically connected to the transmission system and the breakers are closed
For the specific technical questions posed by MISO, the Owners provide the following recommendations:
Finally, communication of a generator going into service is necessary. This communication is the trigger for requirements such as: Schedule 50 Charges, 345kV upgrade reimbursements, updated models and protection settings due to TO within 60 days of commissioning (often not delivered timely or at all when requested by the TO, and NERC registration requirements and associated obligations (e.g. MOD, PRC). In general, communications with ICs regarding the transfer of necessary data associated with the IBR’s final design and subsequent changes becomes more difficult once the GIA has been executed. Most importantly, MISO needs to verify that any performance requirements established here are incorporated in the steady-state and stability models during the DPP pre-queue phase and the stability study during DPP Phase 2. Such requirement verification should include Q-priority flag setting, active and reactive power response and settling times, and elimination of momentary cessation, among other model verification checks against the proposed requirements. In addition, these requirements should be verified with the as-built specifications once the generator has reached Commercial Operation.
Both ATC and Entergy have specific IBR requirements posed publicly available:
https://cdn.misoenergy.org/ATC%20TO%20Planning%20Criteria108210.pdf see Sections 2.1c,
3, and 4.
https://cdn.entergy.com/userfiles/content/operations_information/transmission/fcr/IBR.pdf