In the May 2, 2024, meeting of the Interconnection Process Working Group (IPWG) stakeholders were invited to review and submit feedback on Proposed Replacement and Surplus Application Process BPM-015 Updates.

Please provide feedback on the following:

  • BPM-015 Sections 6.7.2 and 6.7.3        

Please provide feedback by May 16, 2024.


Submitted Feedback

The MISO Transmission Owners (Owners) support the proposed submission process for generation replacements and surplus applications moving to the GI Online Application Portal as presented at the May 2 IPWG.

Muscatine Power and Water (MPW) is in support of the proposed submission process for generation replacements and surplus applications moving to the GI Online Application Portal.

Related Issues

Related Materials

Supplemental Stakeholder Feedback

MISO Feedback Response