Home Planning System Modeling Model Development Schedule

Model Development Schedule

 Date

 Milestone

 TBA Feb 2019 

MISO issues dynamics data request

 TBA Feb 2019  

Stakeholders complete dynamics updates and send to MISO

 TBA Feb 2019 

MISO posts draft PSSE and TSAT models for review. Stakeholder review starts.

 TBA Feb 2019  

Stakeholders comments on draft models due to MISO

 TBA Feb 2019   

MISO incorporates changes from draft review

 TBA Feb 2019

MISO posts final PSSE and TSAT models

 Date

 Milestone

 Responsible     Party

 08/28/2018

 LSE, TO, and GO data request sent

 MISO

 08/28/2018

 Model On Demand reference models posted

 MISO

 09/13/2018

 Generator data due to Model On Demand

 GO

 09/28/2018

 Load profiles  due to Model On Demand

 LSE

 09/28/2018

 Transmission project , BLG profile, and device profile data due to Model On Demand

 TO

 10/17/2018

 Topology and Load Pass  model posted for review

 MISO

 10/17/2018 – 10/31/2018

 Review Topology and Load Pass models    / updates to MOD

 LSE, TO, and GO

 12/28/2018

 Review Pass 3 models posted for review

 MISO

 12/28/2018 - 01/31/2019

 Review of Review Pass models, respond to data checks  / updates to MOD.

 LSE, TO, and GO

 03/15/2019

 Final MTEP models completed / posted

 MISO